TSMC responds to reports of slippage in advanced chipmaking technology

This is not investment advice. The author has no position in any of the stocks mentioned. Wccftech.com contains a file Disclosure policy and ethics.

Taiwanese semiconductor manufacturer (TSMC) has responded to reports claiming that its groundbreaking 3nm (nm) chip manufacturing technology is suffering from delays. Earlier today, reports from research firms TrendForce and Isaiah Research indicated that the TSMC 3nm process would face delays and affect the company’s partnership with US chip giant Intel Corporation – which itself has struggled with manufacturing problems for several years.

TSMC’s response was benchmarked as the company declined to comment on customer requests and stated that manufacturing technology was on schedule.

TSMC stresses capacity expansion plans are on schedule following reports of hiccups

The two reports were the latest in a string of news that has cast doubt on TSMC’s 3nm manufacturing plans. The first news came earlier this year when it was so Initially rumoredThen, he confirmed that the Korean chip maker Samsung Foundry will start production of 3 nm before TSMC.

The statements made by TSMC President Dr. CC Wei made it clear that his company will do so Start making 3nm chips During the second half of this year. TSMC strives to maintain the technological prowess that has made it the world’s largest chip maker.

TrendForce Report He reported that the company believed that the delay in manufacturing 3nm for Intel would hurt TSMC’s capital spending because it could end up cutting spending in 2023. Nor was it shy about blaming Intel, claiming that the released design was initially It caused manufacturing to skip into the first half of 2023 from the second half of 2022 – which has now been pushed back to late 2023.

See also  Concerns about Starfield "skipping Xbox" helped lead Microsoft to buy Bethesda

This in turn has affected TSMC’s capacity utilization estimates – and the company is wary of not being able to idle as it struggles to buy 3nm orders. TrendForce has also shared that Apple will be the first 3nm TSMC customer – with products launched next year, AMD, MediaTek and Qualcomm will produce 3nm products in 2024.

AMD 5nm CPU built by TSMC.

Isaiah Research was more responsive with details of the delay, sharing the number of chips expected to be manufactured initially and the drop after the alleged delay. Isaiah explained that TSMC initially planned to produce 15,000 to 20,000 3nm wafers per month by the end of 2023, but this has now been reduced to 5,000 to 10,000 wafers per month.

However, while addressing the remaining spare capacity concerns due to the decline, the research firm remained optimistic as it indicated that the majority of equipment (80%) for advanced manufacturing processes such as 5nm and 3nm is interchangeable, which means TSMC retains the ability to utilize it for other customers.

TSMC’s response to the entire issue sent to the Taiwanese magazine United Daily News was brief with the company Stating that:

“TSMC does not comment on individual customer business. The project to expand the company’s capacity is proceeding as planned.”

The semiconductor industry, which is currently facing a historic slowdown due to a supply and demand mismatch in the wake of the coronavirus pandemic, has been considering capacity cuts and capital spending for some time. Chinese foundries have lowered average selling prices (ASPs), and Taiwanese chip makers have begun offering different prices for different lots to ensure demand does not diminish.

See also  It is said that the Apple iPhone 14 event will be held in early September

However, TSMC has made no such announcements, and the question of balancing capacity cuts with increased demand, particularly for newer products, remains a thorn in the chip makers’ side, as at one end they risk spending too much on idle machines and on and the other, reducing of revenue harvesting in case of increased demand.